Completed

SE Area New Learning Center, 55.98035
School Name: Maywood Academy HS
6125 Pine Ave., Maywood, CA 90270
Map and Directions

This project is a new neighborhood High School in the cities of Maywood and Huntington Park. Three-story buildings wrap around the two urban streets while allowing the single family residents along the remaining streets a view of the fields. An inner courtyard radiates off the main circulation node and connects the classroom wings. This project has been chosen by the District and Southern California Edison as a Showcase for energy efficiency and sustainability. It was originally planned to include middle school seats which are now being provided by South Region MS #2.


Project Information
Board Member Bennett Kayser
Local Superintendent Rowena Lagrosa
LA City Council N/A
Comm. Outreach Silvestre Quiroz
Owner's Authorized Rep. (OAR) Diana Johnson
Architect WLC Architects
General Contractor Bernards Bros., Inc. / Thompson Pacific
2-Semester Seats 1,215
New Classrooms 45
Site Acres 9.12
Approximate Sq. Ft. 155,897
CHPS Score 50
Schools Relieved Bell HS/Huntington Park HS/Gage MS/Nimitz MS
Schedule
Pref. Site Designated Q2-2001
DSA Approval Q2-2002
NTP Construction Q4-2003
School Occupancy Q3-2006
Cost
Total Budget $ 96,793,443
Project Attachments
Project Images
Project Documents
Questions regarding this project?

Contact Community Outreach at 213-241-6523.
Project last updated on 10/13/2011